Table of Contents

Setting the priority of a primary or backup element

  1. Right-click the element in the Surveyor and select Multiple set.

    Note

    If Multiple set is not visible in the Surveyor right-click menu, make sure the Enable 'Multiple set' Cube user setting is enabled.

  2. In the Multiple set window, do the following.

    1. In the Parameter box, select the general parameter [Priority Level].

    2. Next to Value, specify the new priority.

    3. On the right, select the element(s) to which you wish to apply this priority.

    4. Click Set.

Note
  • Element priority ranges from 1 (highest priority) to 1000 (lowest priority). If priority is set to 0, this means that no priority has been set yet.
  • Alternatively, the element priority can also be set on the General parameters page of each element.